A court may raise a developer's agreed delay compensation to match the buyer's loss despite a lump-sum clause

Abu Dhabi Court of Cassation, Commercial Appeal No. 1104 of 2021, judgment of 7 February 2022

Court
Abu Dhabi Court of Cassationمحكمة النقض - أبوظبي
Case
Abu Dhabi Court of Cassation, Commercial Appeal No. 1104 of 2021, judgment of 7 February 2022
Arabic citation
الطعن رقم 1104 لسنة 2021 تجاري، جلسة 7/2/2022
Topics
Real estate · Commercial law
Laws applied
Civil Transactions Law 1985 (repealed)
The judgment
Read it on adjd.gov.ae ↗ (ADJD judgments service (Abu Dhabi Court of Cassation), Id 58122)
Summary written
31 October 2026
Print

The principle

Under Article 390 of the Civil Transactions Law parties may fix compensation in advance, but the court may, at either party's request, adjust it to equal the actual loss, and any agreement to the contrary is void. A clause in an off-plan sale stating that delay compensation is a lump sum and that the buyer has no further claim does not prevent the court from awarding more where the loss is greater. A buyer who withholds instalments because the developer has failed to deliver on time is exercising the right of retention under Article 247 and owes no agreed compensation for late payment.

The case and the decision

In 2012 a buyer agreed to buy an off-plan villa in Abu Dhabi from a developer for about AED 14.7 million, with delivery in December 2015, later extended to June 2016. The contract provided for delay compensation of 1% plus IBOR on the amounts paid, and clause 7.3 stated that this was a lump sum and that the buyer would have no other claim against the developer for delay. The villa was handed over in May 2020. The buyer sued for about AED 5.2 million; the developer counterclaimed for agreed compensation for late instalments. An expert committee reported that the delay had lasted nearly four years and, according to real-estate engineering practice, that delay compensation should not exceed 10% of the price. The first-instance court awarded about AED 5.1 million; the Court of Appeal reduced the award to AED 1.5 million and rejected the counterclaim.

The developer's appeal was dismissed. The Court held that assessing fault, loss and the evidence, including expert reports, is for the trial court, which is the 'first expert' on damage; compensation covers loss suffered and gain missed without enriching the claimant. Under Article 390 of the Civil Transactions Law the court may, on a party's request, adjust agreed compensation so that it equals the loss, and any agreement to the contrary is void. The Court of Appeal had therefore been entitled, on the buyer's request, to raise the agreed amount to reflect a delay of about four years despite the lump-sum clause. The developer's counterclaim failed because, under Article 247, in bilateral contracts each party may withhold performance while the other fails to perform; the buyer's late payments were a lawful exercise of that right in response to the developer's late delivery.

Why it matters

For off-plan purchases in Abu Dhabi, a developer cannot rely on a capped or 'sole remedy' delay compensation clause to limit liability if the buyer proves greater loss, because Article 390 lets the court adjust agreed compensation to the actual damage. The decision also protects buyers who stop paying instalments once the developer is already in breach.

Laws applied

Articles 247 and 390 of Federal Law No. 5 of 1985 (Civil Transactions Law) — text of articles 247, 390
Decided under this law; it has been replaced by Civil Transactions Law 2025.

In the court’s words

“كما يجوز للقاضي في جميع الأحوال بناءً على طلب أحد الطرفين أن يعدل في هذا الاتفاق بما يجعل التقدير مساوياً للضرر ويقع باطلاً كل اتفاق يخالف ذلك”

Short quotation from the judgment as published by the court. The full judgment is on the court’s official service.

Related judgments

A buyer may rescind an off-plan plot sale and recover the price when the developer has not built the infrastructure

Abu Dhabi Cassation — Commercial 1015/2021 · 17 November 2021

In bilateral contracts, if one party fails to perform, the other may, after notice, seek performance or rescission, and the judge may rescind and award compensation where…

A buyer's agreed waiver of claims for late completion of an off-plan villa was upheld as a valid exemption from contractual liability

Abu Dhabi Cassation — Commercial 311/2022 · 26 May 2022

Parties may include terms that increase, reduce or exclude a party's contractual liability, provided they do not conflict with mandatory rules, public order or morals. Ar…

Courts may not hear claims whose court fees are unpaid; an agent who signs a cheque is personally liable on it

Abu Dhabi Cassation — General Assembly 1/2016 · 28 March 2016

Courts at every level may not hear a claim, appeal or request on which the fees due under Abu Dhabi Law No. 6 of 2013 on court fees (as amended in 2016) have not been pai…

A mortgagee bank may, but need not, enforce against the mortgaged property before other assets

RAK Cassation — Commercial 3/12 JY · 25 September 2017

A secured creditor may enforce first against the mortgaged real estate, but this is an option, not an obligation: it may pursue the debtor's other assets to recover its d…

An assignment of a debt cannot be enforced against the debtor who did not consent to it

Abu Dhabi Cassation — General Assembly 1/2018 · 6 February 2018

The bar on cassation appeals against appellate rulings 'in execution procedures' (Article 173(3) of the former Civil Procedure Law) covers only rulings on the measures th…

Under apparent agency a land sale binds the owner, and only the owner can claim under it

RAK Cassation — Civil 14/13 JY · 9 April 2018

A contract may be made through an agent, whose authority under the agency agreement governs his relationship with the principal; a third party must normally check the age…

Source. Summary written by Polaris from the judgment published by the Abu Dhabi Court of Cassation on adjd.gov.ae (ADJD judgments service (Abu Dhabi Court of Cassation), Id 58122), read on 31 October 2026. Party names are anonymised in the court’s publication.
Published for general information by Polaris Corporate Services FZ-LLC. It is not legal advice. This page is a summary written by Polaris; it is not the judgment and is not an official translation. Read the judgment on the court’s official service before relying on it. A judgment decides the dispute before the court; its weight in a later case depends on the court, the facts and any later change in the law or in the court’s own case law.