Abu Dhabi Court of Cassation, Commercial Appeal No. 1380 of 2021, judgment of 10 February 2022
The main construction contract creates no rights for a subcontractor against the employer. Following the employer's instructions does not make the subcontractor a party to the main contract or entitle it to compensation for its breach, and an employer that pays part of a subcontractor's dues does not thereby become a party to the subcontract. Being named in a contract does not make someone a party to it. Where the contract fixes no interest rate on a liquidated sum paid late, interest runs at the market rate at the time of dealing, capped at 12% a year, and the judge assesses it if the creditor cannot prove that rate.
Under a 2018 subcontract worth AED 67.5 million, a subcontractor carried out the mechanical, electrical and plumbing works for a staff accommodation camp being built for the project owner. After completion and the municipality's completion certificate in June 2020, it sued the main contractor and the owner jointly for about AED 13.59 million and AED 1 million for lost profit. The owner had paid it AED 836,014 directly, which was deducted from the main contractor's dues. The main contractor counterclaimed for about AED 36.8 million. The courts below held that the claim against the owner was inadmissible because it was not a proper defendant, awarded AED 5,135,358 against the main contractor with interest at 1% a year, and dismissed the counterclaim.
The Court of Cassation dismissed the subcontractor's appeal. The main contract does not create rights for the subcontractor against the employer, and the subcontractor does not become a party to it by carrying out the employer's instructions during the works. Only a person who expresses a will matching another's to create, transfer, modify or extinguish an obligation is a party; not everyone mentioned in a contract is. The owner was not a party to the subcontract, and its agreement to pay part of the subcontractors' dues did not make it one. Under Articles 872, 877, 878 and 885 of the Civil Transactions Law, whether the contractor completed the works to the agreed specifications and on time is for the trial court, which may rely on the expert's report. Under Articles 76, 77, 88 and 90 of the Commercial Transactions Law, interest on a liquidated sum paid late runs from the due date at the agreed rate or, failing that, the market rate up to 12%; as the subcontractor had not proved the market rate, the court's 1% was lawful. The claim for compensation failed because the additional work was needed to complete the project and the subcontractor had not carried out post-handover maintenance.
Subcontractors on UAE projects generally have to look to the main contractor for payment; direct payments by the owner and site instructions from it do not create a contractual claim against the owner. Without an agreed interest rate or evidence of the market rate, late-payment interest may be set well below 12%.
| Articles 872, 877, 878 and 885 of Federal Law No. 5 of 1985 (Civil Transactions Law) — text of articles 872, 877, 878, 885 Decided under this law; it has been replaced by Civil Transactions Law 2025. |
| Articles 76, 77, 88 and 90 of Federal Law No. 18 of 1993 (Commercial Transactions Law) Decided under this law; it has been replaced by Commercial Transactions Law. |
“ان عقد المقاولة الأصلي لا ينشئ أية حقوق للمقاول من الباطن قبل صاحب العمل”Short quotation from the judgment as published by the court. The full judgment is on the court’s official service.
An assignment of a debt cannot be enforced against the debtor who did not consent to it
The bar on cassation appeals against appellate rulings 'in execution procedures' (Article 173(3) of the former Civil Procedure Law) covers only rulings on the measures th…
A purchase order is a binding contract once essential terms are agreed, and its storage-charge clause is enforceable
A contract is formed when an offer is matched by acceptance, expressed in words, writing, conduct or any behaviour that leaves no doubt of consent (Articles 125, 129 to 1…
A tenant in control of gas tanks is strictly liable for a fire that spreads to a neighbour's warehouse
Under Article 316 of the Civil Transactions Law, whoever has actual control of things requiring special care, owner or not (such as a tenant), is liable for the harm they…
A concrete supplier was not liable for a building collapse that experts attributed to design and site supervision failures
Under Articles 878 and 880 of the Civil Transactions Law, the contractor and supervising engineer guarantee, as an obligation of result, against total or partial collapse…
Under the law then in force, an insurer's diya liability for a female victim was half that for a male
Diya (blood money) for death or bodily injury is governed by Islamic law under Article 1 of the Penal Code of 1987 and Law No. 3 of 1996, applying the Maliki school. The …
A debtor who claims insolvency must prove it; the court must rule on the claim as framed and as characterised on cassation
Insolvency (الإعسار) exists where a debtor's debts equal or exceed his assets; once established, the court may place him under interdiction under Articles 401 and 402 of …
Whether you are establishing a new venture, restructuring an existing enterprise, or exploring residency pathways — we are here to advise.